Nepal is considering a change to its securities law that would give statutory backing to the construction threshold for hydropower share offers and set out safeguards for investors financing unfinished projects.
The proposal forms part of a draft amendment covering investment and infrastructure laws. It has not been enacted, and the government has yet to decide whether to proceed through an ordinance or a bill in Parliament.
The central construction condition is not new. The Electricity Regulatory Commission already requires projects under construction to reach at least 50 per cent physical progress before their companies can issue shares to the public. The draft would incorporate that threshold into the Securities Act for initial public offerings, the first public sale of a company’s shares.
Under the proposal, a project meeting the certified construction threshold and the other requirements could not have its application rejected solely because commercial electricity generation had not started. Reaching halfway through construction would not, by itself, satisfy every condition for an offering.
Checks on construction and funding
Construction progress would have to be verified by an independent, qualified technical evaluator. That assessment would establish the stage of the work, rather than certify that the remaining construction had been completed or that electricity production was already under way.
Companies would also have to disclose the total project cost, the work still outstanding and the additional funding needed to finish it. Confirmed sources of finance would form part of the information supplied to prospective shareholders.
Those details would put the construction percentage alongside the financing position. A project could have completed a substantial amount of physical work while still needing further money for the remaining stages, making the funding requirement a separate part of its disclosures.
The prospectus, the document setting out the share offer, would need to describe construction progress and major project risks. These would include possible delays and cost overruns, so that the offer was not presented simply as a percentage of work completed.
Developers would have to disclose the status of power purchase agreements, generation licences and other necessary regulatory approvals. They would also need to state the estimated completion date and when commercial electricity generation was expected to begin.
A clear plan for spending the money raised from the public would be required. The draft also provides that IPO proceeds must be used for the approved purposes of the project, linking the fundraising proposal to the work it is intended to finance.
The Securities Board of Nepal would be able to set additional requirements to protect investors. The proposed framework therefore combines a construction threshold with technical checks, financing information and controls on how public investment is used.
Disagreement over when shares should be sold
The debate overlaps with a separate draft from the securities board on general eligibility for public offerings. That proposal calls for a record of continuous business operations, while allowing different standards across sectors. Hydropower promoters have objected that such a requirement could restrict access to equity during construction.
Share investor Keshav Koirala favours a stricter approach, arguing that hydropower companies should wait until they begin generating electricity before selling shares to the public.
Ganesh Karki, a former president of the Independent Power Producers’ Association, Nepal, argues that developers need substantial capital during the early stages of a project. He favours stronger construction oversight and protection of investors’ money rather than preventing fundraising before generation starts.
Investor and analyst Subas Chandra Dhungana argues against applying the same standard to every project. His preferred approach would take account of generating capacity and the deadline for starting production, particularly because large projects can take years to complete.
The draft leaves these questions within a proposed legal framework, not an implemented change. No timetable has been established for the amendment to take effect.