The Civil Aviation Authority has opened a consultation on proposals that would allow up to approximately £700 million in early Heathrow expansion costs to be recovered through airport charges, including spending covered by an earlier decision.
The regulator estimates that recovering the total over 20 years would be equivalent to around 60 to 70 pence per passenger journey. It stressed that the figures are indicative and will be updated before a final decision.
Published on 25 November, the consultation covers work by Heathrow Airport Limited and rival promoter Heathrow West Limited on applications for a Development Consent Order, the planning consent sought for the expansion proposals.
The package concerns early development expenditure from the beginning of 2025 to the middle of 2027. It does not approve construction of a third runway, decide which expansion scheme should proceed or guarantee that all the proposed spending will be recovered.
What the spending proposals cover
Heathrow Airport Limited has told the CAA it proposes to incur up to £304 million during the first six months of 2027. The company says this would maintain the option of submitting its Development Consent Order application by the end of that year.
Heathrow West forecasts approximately £46 million of expenditure during 2026 and a further £35 million in the first half of 2027, according to the regulator.
A CAA decision in July already permitted recovery of certain early expansion costs incurred by Heathrow Airport Limited during 2025 and 2026, and by Heathrow West up to November 2025. The approximately £700 million total combines those earlier allowances with the costs proposed in the new consultation. It is not £700 million of wholly new expenditure.
The regulator describes the amounts as ceilings. In its consultation document, it says a cap should not be treated as an approved budget, a spending target or an automatic entitlement to recover expenditure up to that amount.
Actual costs would undergo a retrospective efficiency review. The final recoverable amount could be lower, with only eligible and efficiently incurred expenditure allowed under the proposed arrangements.
Passenger costs and consumer protections
The CAA’s 60 to 70 pence estimate would be additional to current average Heathrow airport charges of around £26 per passenger. These are airport charges, not a confirmed new surcharge on passenger tickets, and the consultation has not settled the final recovery arrangements.
The authority says expansion has the potential to benefit consumers by increasing capacity, route choice and competition between airlines. It also acknowledges that allowing more than one promoter to recover development costs would increase the costs ultimately borne by Heathrow consumers.
Its proposed approach rests on the expectation that competition between expansion promoters would deliver consumer benefits greater than those additional costs. Each proposal would need to be sufficiently mature, credible and deliverable to support that competition.
Tim Johnson, the CAA’s director of consumers and markets, said the regulator’s role was to support decisions on Heathrow expansion while protecting consumers’ interests. He said credible proposals needed clear evidence that costs were efficient, appropriately justified and delivered value.
Proposed safeguards include defined categories of eligible spending, promoter-specific caps, regular transparent cost reporting and independent scrutiny. The CAA also wants information sharing and arrangements to prevent unnecessary duplication between promoters. It says inefficiently duplicated costs would not be recoverable.
Further decisions due in 2027
The regulator expects to publish another consultation on recovery of early costs through June 2027 next spring, followed by a final decision in summer 2027.
Further expenditure is likely after June 2027, the CAA says, but the current proposals do not address its recovery or create a presumption that it will be recoverable. The authority describes the package as limited support for developing credible expansion proposals, rather than an open-ended commitment to fund either promoter through to a planning decision.