Ealing Council is due to consider testing market interest in six housing sites where work stopped after contractor failures in 2023. A separate proposal for a 100-home council scheme at Mandeville Parkway in Northolt is also scheduled for consideration on 7 October.
The stalled sites are Chesterton and Evesham Close and Wood End in Greenford; Norwood Road and Shackleton Road in Southall; Dean Gardens in West Ealing; and the Southall Market car park development. Work across the programme stopped after contractor failures in 2023. The sites have since been assessed for possible routes back into development.
Before settling on a route forward, the council has undertaken technical, legal and financial checks. The proposed next step is to market the sites as a package and invite interest and competitive offers, helping establish whether there is a viable way to get the schemes moving again and on what terms.
The six projects were originally expected to provide 230 homes, including 174 for London Affordable Rent. That figure describes the earlier plans, not a guaranteed total for any future scheme. The market exercise is intended to test options; it does not itself secure a replacement builder, approve a design or commit the council to construction.
Nor is the council seeking a decision to sell the sites at this stage. If the market test is approved, information and offers would be assessed and brought back in a further report with recommendations about what should happen next. The future of each site will depend on what the exercise shows about deliverability and the proposals brought forward. No completion dates for the six sites have been set out.
The distinction matters because the stalled schemes have not all reached the same point. Some structures were partly built when work stopped, and the council has been reviewing technical and financial considerations rather than simply restarting the previous contracts. The October decision would open a process for testing options, not confirm that existing construction can be resumed or that all 230 homes will be delivered as first planned.
Mandeville Parkway takes a separate route
On the same date, Cabinet is due to consider the next stage of the proposed Mandeville Parkway development, which is planned to provide 100 new council homes for social rent. The scheme would use land around the Northolt Park estate and include a mix of apartments and townhouses in different sizes.
Plans also include improved public space, landscaping, play areas and shared outdoor spaces. The homes are intended to meet high energy-efficiency standards, with the aim of reducing emissions and future household energy bills.
The decision under consideration is an early delivery step: approval to begin the process of finding a contractor and securing the funding needed before construction. It would not award a construction contract. A further Cabinet report would be required before any building contract could be let, and the project remains subject to planning permission and procurement.
If the required approvals are secured and the procurement proceeds, construction at Mandeville could begin in 2028, with the homes expected to be ready in 2030. Those dates are projections rather than confirmed start or completion dates.
The two proposals therefore address different stages of Ealing’s housing programme. The six stalled sites would enter a market-testing exercise before a future recommendation is made, while Mandeville would move towards contractor and funding arrangements for a new scheme. Neither decision would mean that homes are immediately ready to build, but both would determine what work can follow and what further approvals are needed.