Bexley care-home appeal dismissed over uncertainty about resident carer

Bexley care-home appeal dismissed over uncertainty about resident carer

A planning appeal concerning a proposed small residential care home in Bexley has been dismissed after a government-appointed Inspector found that the evidence did not clearly establish how a resident carer would live and work at the property.

The appeal concerned 2 St Edmunds Close in Bexley and followed the council’s refusal to issue a certificate of lawful use or development. The certificate sought would have confirmed whether the proposed arrangement could lawfully operate without a fresh planning permission application. The Inspector’s decision, dated 21 September, leaves that certificate refused.

What the proposed use involved

The application described a residential care home for up to four young people aged 16 to 18 who have learning disabilities or mental health problems and need care, while living together as one household. It was put forward as a Class C3(b) use, a planning category for a dwellinghouse occupied by no more than six residents living as a single household where care is provided.

The property’s existing lawful use was understood to be Class C3(a), the ordinary dwellinghouse category. Moving from one purpose within the same use class does not necessarily amount to development requiring planning permission. That was the question at the centre of this case, rather than a decision on a conventional planning application for a new building or extension.

In dismissing the appeal, the Inspector did not make a finding about the merits of providing care for young people or about the needs of any individual. The decision instead turned on whether the documentation supplied demonstrated, on the balance of probabilities, that the specific proposed operation would remain within Class C3(b).

Resident carer evidence was not clear enough

The supporting material referred to one permanent employee living at the house and providing specialist care and support. However, appeal material also referred to one full-time employee working a shift pattern to provide care over 24 hours. The Inspector concluded that those accounts were not sufficiently clear or consistent.

A 24-hour shift pattern would logically involve more than one carer, the decision said. It did not set out how many carers would be involved, what hours they would work or whether any carer would genuinely be resident at the house. That detail mattered because the proposed residents were children and the household case relied on there being a resident carer to run a functioning household.

The Inspector also said there was not sufficiently precise information about the young people’s needs or the likely nature and extent of visits by professionals or other staff. Without that information, the decision found it was not possible to assess whether the proposed operation would change the planning character of the property.

As a result, the applicant had not shown that the proposal would fall within Class C3(b), nor that it would avoid a material change of use requiring planning permission to be lawful. The ruling does not mean that every care arrangement for young people must fall outside that use class. It addresses the evidence supplied for this particular proposal at this particular address.

What the ruling does and does not decide

A lawful development certificate determines whether a described proposal is lawful in planning terms; it is not the same as a grant of planning permission. The dismissal means that the certificate requested for this arrangement has not been issued. It does not give planning permission for the use, nor does it determine a different future proposal supported by fuller evidence.

The Inspector made the decision on written submissions and said a site visit was not necessary because the appeal concerned the legal status of the proposed use. Any later application would be assessed on the material then submitted and under the relevant planning process.

A separate application by the appellant for a full award of costs against Bexley Council was also refused. The Inspector accepted that the council had not decided the certificate application within the statutory timeframe and said a proper explanation should have been given once the delay became apparent. But the decision found that the delay had not caused unnecessary or wasted expense in the appeal process, because the substantive disagreement would still have led to an appeal.

For Bexley residents, the case illustrates why the operational detail behind a proposed care-home use can be central to planning classification. The outcome rests on the information presented, not on a general conclusion about the suitability of care homes in residential areas.

Pin It on Pinterest