Edinburgh housing schemes change delivery partners after cost and risk-sharing talks fail

Edinburgh housing schemes change delivery partners after cost and risk-sharing talks fail

Edinburgh’s plans for more than 1,000 homes at Fountainbridge and Meadowbank are moving to alternative delivery arrangements after the council’s partnerships with their chosen developers ended. The two schemes together have planned capacity for 1,169 homes, including affordable housing, but both are delayed.

The contractual difficulties differ between the sites. At Fountainbridge, standard terms could not be agreed on how development risk would be shared. At Meadowbank, the partnership ended after a failure to reach agreement on costs. The council intends to continue both developments rather than abandon the housing proposals.

Fountainbridge moves to another supplier

The Fountainbridge project would redevelop a former brewery site beside the Union Canal into a mixed-use neighbourhood. Its masterplan, approved in 2016, provides for 464 homes and 10,000 square metres of office space.

Of the proposed homes, 186 would be affordable. That allocation comprises 115 homes for social rent and 71 for mid-market rent. These remain planned homes, rather than properties that have already been completed or made available to tenants.

Cruden Homes and its development partner Buccleuch Property were selected for the project in 2021. Cruden Homes (East) Limited and Buccleuch Property had been awarded a £1.1 million pre-development services contract for the site.

The contractor withdrew from the development agreement after standard terms on risk sharing were not agreed. The council is progressing the project through another supplier, although the change has required a delay.

By September, the Fountainbridge contractor had withdrawn and £13 million of budgeted expenditure was being moved into future years as the delivery arrangements changed. The November position continues to include the shift to another supplier and the delay to the scheme.

Meadowbank’s affordable housing comes first

Meadowbank’s plans cover 705 homes around the rebuilt sports centre. The development was prepared by a consortium led by Graham, with Miller Homes and Panacea Property Development, which became the pre-development partner in 2022.

The planned accommodation mix includes 216 one-bedroom homes, 337 two-bedroom homes, 138 three-bedroom homes and 14 studios. Within the overall total, 27 properties would be wheelchair accessible. The neighbourhood’s design combines energy-efficient homes with low-car and low-carbon infrastructure.

The masterplan provides for 35% of the homes to be affordable, with a majority of that affordable allocation intended for social rent. The council is working with one of its framework contractors to deliver the affordable housing as the first stage of the development.

The Meadowbank partnership ended by mutual agreement after terms for the delivery stage could not be settled. The agreement was terminated in line with its contractual arrangements, and the development is to proceed with an alternative supplier.

Meadowbank was already significantly delayed in September. At that point, £32.9 million of site remediation and affordable housing construction had been anticipated during 2026-27, but agreement on costs had not been reached. The partnership had ended by the finance and resources committee’s 17 November meeting.

Completion dates remain projections

Both sites are listed as delayed in the council’s 2026-27 housing capital-monitoring programme. Their latest anticipated completion dates remain March 2030. Those dates are forecasts, not confirmation that the homes will be ready by then.

The changes concern the arrangements for delivering the developments, rather than the completion of new homes. They also sit within a wider housing programme in a city where the council declared a housing emergency in November 2023.